by HaloSep | Jan 22, 2020 | Progress update
We have had good progress in the construction of the HaloSep demonstration plant at Vestforbrænding. We have finalized the concrete and steel foundations and we have started mounting the tanks in place. Each tank, color-coded according to its function in the process,...
by HaloSep | Oct 30, 2019 | Progress update
We have finished the floor preparation and piling work. The next step is to build the concrete machine foundations so that we can install the various pieces of equipment required for HaloSep. As the work progresses, we will be making a time-lapse video so that the...
by HaloSep | Sep 5, 2019 | Progress update
Construction of the HaloSep process started on September 2nd, 2019 with drilling of holes for the supporting pylons. For more information, see the Vestforbrænding web page.
by HaloSep | Jun 19, 2019 | Progress update
On Wednesday June 12th, we welcomed our external monitor from the LIFE programme to Vestforbrænding. We spent the day going over the project status as well as discussing the construction plans and plans for future exploitation. We gave a tour of the plant and showed...
by HaloSep | Jun 5, 2019 | Progress update
After months of procurement activities, we are proud to announce that contracts for all major items of equipment have been signed. We had a successful kick-off meeting with our main contractor, Eurocon, on May 23rd. The next step will be to start construction of the...