We have had good progress in the construction of the HaloSep demonstration plant at Vestforbrænding. We have finalized the concrete and steel foundations and we have started mounting the tanks in place. Each tank, color-coded according to its function in the process, is delivered “just-in-time” from nearby storage. Skilled operators carefully maneuvre each tank into its designated position. There have been some tight fits, but staff and contractors work together to creatively resolve each issue.